We started moving equipment into the new 50'x80' machine shed today. Took 18 months to have a usable space, due to design/contractors, etc.
First in was the swather.The computer generated diagram in pic #1 has some pieces 3" apart. We'll find out soon if it's all going to fit as it says. Getting enough room for the tractor to maneuver the equipment into position is a challenge. We won't be done with the combine and bean head until mid to late October. Until then we can only put in a few more pieces.
It's going to fill up fast. The tractors, as well as the boom lift, trailer, grain cart, and trucks, will fill up the old shed (40'x120').
The swather, pictured below, is noted with tiny print in the lower left hand corner of the above diagram. |
I'm already thinking that I'll have to add a lean-to shed - outside of the one long wall that doesn't have a door on it - so that I can easily fit everything.